Hamilton Tarmac have recently completed the above Project in conjunction with the Client, Ayrshire Roads Alliance and South Ayrshire Council

The Project called for the construction of approximately 1000 metres of 3-metre-wide segregated cycleway and 2-metre-wide footway from Dundonald Road to North Drive, Troon, South Ayrshire.

Included in the works was the requirement for all excavated material to be removed from site for recycling and imported Class 6F5 material to be re-cycled.  Hamilton Tarmac was able to comply with both requirements using their sister company’s recycling centre at their Dundonald Operating Centre, less than 5 miles from the site.

The surface course through the Marr College playing field area was a laid using a flexible porous material which consisted of re-constituted rubber tyres mixed with a polymer resin and laid 40mm thick.

The works were completed within time and on budget.